Once Synthesis placement cts_sta is completed, is it possible to start from resizer or all steps hav...
m
Once Synthesis placement cts_sta is completed, is it possible to start from resizer or all steps have to be completed again using new configuration parameters
There is the following Error [ERROR GRT-0119] Routing congestion too high. Check the congestion heatmap in the GUI and load /media/psf/Home/Downloads/sljt1.comp.xfer/backupcvs/hcb1/hcb/LDPCENCDEC/openlane/ldpcEncDec/runs/24_03_18_20_16/tmp/routing/resizer-routing-design-congestion.rpt in the DRC viewer. Error: resizer_routing_design.tcl, 46 GRT-0119 child process exited abnormally
v
check why/where congestion occurs. Based on congestion you've start from floorplan/placement stage again
m
I would like to know how I can start from floorplan I generally do make user_proj_example which runs from linting
v
raise a github issue by attaching
issue_reproducible
generated by the flow
m
2104 updated the issue