Hello @mehdi @Tim Edwards, I hope you are doing fine.
Unfortunately, after doing a detailed analysis of the remaining tasks and the available resources, our team in Chile realized it would be not possible to deliver the SAR design for the tapeout (we still don't have a working top level simulation, and therefore can't do block-level optimization and layout). This considers the fact that the university is closed until march , as I already informed to @Boris Murmann some days ago.
We can commit to the following for the date proposed:
• Full LDO design ready for tapeout and integrated to the pad ring
• Help making possible that the top including pad ring and blocks for LTC2 is properly carried out to tapeout.
• Regarding the SAR, we hope we can finalize it and deliver it in a future gf180 mpw free run.
Please excuse the late change of plans, but it has been hard to deal with the gf180 technology and changes in our team.